• CBS Concreting

Unisurge Farbound

Updated: Apr 19

Project Specification

Concrete Pour Size 5,000 ㎡

Tolerance achieved FM2 Special

Concrete Laid per Day 200 ㎥


Our team installed internal concrete floors for our clients at Uniserge, Farboud innovation park. We achieved 200m3 per day, laid through Laser Screed to FM2.


For this project we completed 2 Buildings in 2 phases tailored to the clients schedule and both sites were completed within 5 working days.


We provided Isedeo Permanent Formwork Joints laid to +/- 2mm and sealed with Proseal.


“CBS installed concrete across two sites for us. They're quick, tidy and professional, completed our jobs in five days"