• CBS Concreting

Cardinal Maritime New Warehouse

Updated: Apr 19

Project Specification

Concrete Pour Size 6,000 ㎡

Tolerance achieved SR3

Concrete Laid per Day 200 ㎥


Our team installed concrete flooring for the Cardinal Maritime new internal warehouse in just 3 months (1 month ahead of schedule).


We completed 2,200m2 using Laser screed lay and 600m2 of Raised Decking Floor with a Powerfloat finish.


We also provided 5,000m2 Brush Finish for the External Yard.


“CBS installed our warehouse concrete floor and completed the project one month ahead of schedule"

Project Summary











































7 views0 comments